Big George's big boost for the North West

27 Oct 2026



Continuing our ten-year programme to upgrade the Vyrnwy Aqueduct, an innovative pipe-pushing machine nicknamed ‘George’ is playing a key role in the latest phase of our £260 million programme to ensure we continue to supply top-quality drinking water to the North West.

The custom-built machine is being used to push a new pipe into an existing 4.3km Victorian pipeline near Delamere Forest, between Tarporley and the Abbey Arms. This section is due for completion by March 2027.

Named after George Deacon - the engineer who designed the Vyrnwy aqueduct in the late 1880’s - George was developed with specialist manufacturers and is now the UK's largest and most powerful pipe pusher. George weighs in at a mammoth 200 tonnes and can push pipes up to 2km in a single installation!

How George is helping us and the environment

This type of technology allows our teams to install modern pipework while significantly reducing the amount of excavation needed compared with traditional construction methods, helping to minimise disruption for local communities and the environment.

Will Eyre, our Regional Delivery Manager, said: "George is a great example of how innovation is helping us deliver one of the largest and most complex water infrastructure projects currently under way in the UK.

"We're modernising a Victorian aqueduct that supplies drinking water to around one million people every day, helping ensure it continues to provide high-quality water for future generations."

The Vyrnwy Aqueduct Modernisation Programme (VAMP) explained

This work is supporting the upgrade to the Victorian aqueduct that carries water from Lake Vyrnwy in Wales to Prescot in Merseyside. The investment will help improve water quality and ensure a critical piece of infrastructure continues to serve our customers for generations to come.

The Vyrnwy Aqueduct comprises three parallel pipelines stretching from Powys to Merseyside, travelling 110km. The earliest pipeline, known as Line 1, was constructed between 1881 and 1892, with Line 2 following just over a decade late

As part of the modernisation programme, we’re currently relining 102km of lines between Malpas and Prescot by installing new 900mm polyethylene (PE) pipe inside the original cast iron pipelines. Creating this "pipe within a pipe" will help maintain water quality and reduce the risk of discolouration caused natural sediment that built up over time.

Marc Reynolds, Regional Director at North & Wales, OCU Group, added: “George is a practical example of how investment in specialist equipment, combined with the expertise of our teams, can help overcome complex engineering challenges.

“Installing longer sections of pipe with fewer excavations allows us to work more efficiently while reducing disruption for local communities and the impact on the surrounding environment. We’re proud to be working with United Utilities to modernise this important asset, helping ensure it continues to provide reliable, high-quality water supplies for generations to come.”

The project presents several significant engineering challenges, with the aqueduct crossing railways, motorways, rivers, canals, and major roads along its route. The work is also being carried out while the aqueduct remains operational, ensuring customers continue to receive a reliable water supply throughout construction.

Alongside the relining programme, we’ve also completed the cleaning of 36km of the aqueduct's third pipeline using an advanced technique. Originally developed for the oil and gas industry, the method uses significantly less water than traditional cleaning approaches and has helped save hundreds of megalitres of water while reducing tanker movements and carbon emissions.

The programme is now around 60 per cent complete and remains a key part of our long-term investment in resilient, high-quality drinking water supplies across the North West.

Construction on the Vyrnwy Aqueduct Modernisation Programme (VAMP) is due for completion in 2028.

To find out more, visit: Vyrnwy Aqueduct Modernisation Programme.