Haweswater Aqueduct Resilience Programme

HARP is a major scheme to maintain drinking water supplies across Cumbria, Lancashire and Greater Manchester for future generations. The Haweswater Aqueduct is a 110km pipeline which runs from the Lake District, through Lancashire and into Greater Manchester. Completed in the 1950s, the pipeline needs essential maintenance to ensure it can continue to supply customers for generations to come.

Latest Update

Our biggest infrastructure upgrade in over a century is underway, helping to create a more resilient water and wastewater network across the North West, bringing environmental transformation that improves 500km of the region’s rivers, creating new jobs and supporting local businesses. 

The Haweswater Aqueduct Resilience Programme (HARP) is a major part of our upgrade plans which will involve the replacement of over 50 kilometres of tunnel sections on the aqueduct. The programme is being delivered by Cascade Infrastructure and their design and build partner STRABAG UK. 

Detailed design is now taking place following the completion of ground investigation and environmental survey works.

The initial programme of work has now been developed. Due to the scale of the programme, the works will be delivered in phases. This means that start and finish dates of works will vary by location and to ensure efficient delivery, may be subject to change as works progress. As this is the case, we will regularly update this page with the latest information.

You can find the full details of our plans at www.harpinformation.co.uk

Location Expected start on site date Expected completion date

Bury, Greater Manchester

Woodgate Hill Compound

Autumn 2026

2032

Haslingden, Lancashire

Townsend Fold Compound

Spring 2028

2032

Haslingden, Lancashire

New Hall Hey Compound

Summer 2027

2032

Haslingden, Lancashire

Haslingden Road Compound

Road works summer 2026

Compound start autumn 2026

2033

Huncoat, Lancashire

Bolton Avenue Compound

Summer 2027

2032

Ribble Valley, Lancashire

Braddup Compound

Summer 2027

2033

Ribble Valley, Lancashire

Bonstone Compound

Summer 2027

2033

Ribble Valley, Lancashire

River Ribble and River Hodder Crossings

Early 2027

2027

Ribble Valley, Lancashire

Pimlico Link Road Park and Ride

Early 2028

 

Ribble Valley, Lancashire

Newton-in-Bowland Compound

Summer 2027

2035

Bowland, Lancashire

Lower Houses Compound

Late 2027

2035

Cumbria

Stangana Compound

Late 2026

2033

Cumbria

Beela Compound

Late 2028

2033

Cumbria

Kinn Road Compound

Spring 2029

2035

Cumbria

Tebay Road Compound

Autumn 2029

2035